GB 50372-2006 炼铁机械设备工程安装验收规范 (英文版)
中华人民共和国住房和城乡建设部更新时间:2020-09-24 18:15:53
最新章节:19.2 Overall Leakage Test for Blast Furnace System封面
版权页
Announcement of Ministry of Construction of the People's Republic of China
Forward
1 General Provisions
2 Basic Provisions
3 Equipment Foundation,Anchor Bolts and Padding Plate
3.1 General Provisions
3.2 Equipment Foundation
3.3 Anchor Bolt
3.4 Padding Plate
4 Mobilization of Equipments and Materials
4.1 General Provisions
4.2 Equipments and Elements
4.3 Raw Materials
5 Process Structural Steelwork
5.1 General Provisions
5.2 Welding
5.3 Connection of High-strength Bolts
5.4 Fabrication of Frame,Corridors,Truss
5.5 Fabrication of Large-diameter Coil-welded Steel Pipe
5.6 Fabrication of Shell
5.7 Installation of Frame
5.8 Installation of Corridors,Truss
5.9 Installation of Shell
5.10 Installation of Large-diameter coil-welded steel pipe
5.11 Painting Works for Process Steel Structure
6 Installation Engineering of Blast Furnace Body Equipment
6.1 General Provisions
6.2 Furnace Body Cooling Equipment
6.3 Tuyere Device
6.4 Slag hole Device and taphole sleeve
6.5 Gas Sampling Device
6.6 Commissioning of Gas Sampling Device
6.7 Throat Steel Brick
6.8 Furnace Top Guard Shield
7 Installation Engineering of Blast Furnace Bell-less Top Equipment
7.1 General Provisions
7.2 Transmission Gear Box with Distribution Chute
7.3 Bellows
7.4 Valve Box
7.5 Charging Bucket
7.6 Receiving Hopper
7.7 Commissioning of Bell-less Charging Equipment
7.8 Vertical Detecting Device
7.9 Commissioning of Vertical Detecting Device
7.10 Blow-off valve,Equalizer valve on top
7.11 Commissioning of Blow-off Valve,Equalizing Valve
7.12 Top Ignition Device
7.13 Commissioning of Top Ignition Device
7.14 Throat spray device
7.15 Throat Temperature Measuring Device
8 Installation Engineering of Feeding Equipment
8.1 General Provisions
8.2 Electric Belt Discharging Car
8.3 Commissioning of Electric Belt Discharging Car
8.4 Weighing Hopper
8.5 Commissioning of Weighing Hopper
8.6 Coke Cutter
8.7 Commissioning of Coke Cutter
9 Installation Engineering of Charging Equipment
9.1 General Provisions
9.2 Skip Charging Equipment
9.3 Commissioning of Skip Charging Equipment
- APP免费
9.4 Belt Charging Equipment
- APP免费
9.5 Commissioning of Belt Charging Equipment
- APP免费
10 Installation Engineering of Tuyere Platform and Cast House Equipment
- APP免费
10.1 General Provisions
- APP免费
10.2 Hydraulic Clay Gun
- APP免费
10.3 Commissioning of Hydraulic Clay Gun
- APP免费
10.4 Taphole Machine
- APP免费
10.5 Commissioning of Taphole Machine
- APP免费
10.6 Slag Stopper
- APP免费
10.7 Commissioning of Slag Stopper
- APP免费
10.8 Slag,Iron Chute and Gate
- APP免费
10.9 Swinging Iron Nozzle
- APP免费
10.10 Commissioning of Swinging Iron Nozzle
- APP免费
10.11 Main Chute Cover Carriage
- APP免费
10.12 Commissioning of Main Chute Cover Carriage
- APP免费
11 Installation Engineering of Hot-blast stove Equipment
- APP免费
11.1 General Provisions
- APP免费
11.2 Snout and Supports
- APP免费
11.3 Sleeve-type Burner and Combustion Air Fan
- APP免费
11.4 Commissioning of Combustion Air Fan
- APP免费
11.5 Valves of Hot-blast Stove
- APP免费
11.6 Commissioning of Hot-blast Stove Valve
- APP免费
12 Installation Engineering of Blast Furnace Air-blowing Equipment
- APP免费
12.1 General Provisions
- APP免费
12.2 Axial Blower
- APP免费
12.3 Commissioning of Axial Blower
- APP免费
12.4 Air Filter
- APP免费
12.5 Overall No-load Commissioning of Air Filter
- APP免费
12.6 Dehumidifier
- APP免费
12.7 Valve
- APP免费
12.8 Commissioning of Valve
- APP免费
13 Installation Engineering of Gas Purification Equipment
- APP免费
13.1 General Provisions
- APP免费
13.2 Gas Shut-Off Valves of Dust Remover
- APP免费
13.3 Commissioning of Gas Shut-off Valves of Dust Remover
- APP免费
13.4 Ash Valve of Dust Collector and Gas Ash Mixer
- APP免费
13.5 Commissioning of Ash Valve of Dust Collector and Gas Ash Mixer
- APP免费
13.6 Valve Group for Gas Pressure Regulating
- APP免费
13.7 Commissioning of Gas Pressure-regulating Valve Unit
- APP免费
13.8 Pressure-regulating Device of Circumferential Weld Scrubber
- APP免费
13.9 Commissioning of Pressure-regulating Device of Circumferential Weld Scrubber
- APP免费
13.10 Gas Blow-off Valve
- APP免费
13.11 Commissioning of Gas Blow-off Valve
- APP免费
13.12 Horizontal Silencer
- APP免费
13.13 Blade-type Inserter
- APP免费
14 Installation Engineering of Blast Furnace Pulverized Coal Injection(PCI)Equipment
- APP免费
14.1 General Provisions
- APP免费
14.2 Bin-type Pump
- APP免费
14.3 Raw-coal Bin and Pulverized Coal Tank
- APP免费
14.4 Pulverized Coal Collector
- APP免费
14.5 Injection System
- APP免费
15 Installation Engineering of Slag Treatment Equipment
- APP免费
15.1 General Provisions
- APP免费
15.2 Blowing Box and Water Slag Tank
- APP免费
15.3 Rotary-drum Slag Granulation Equipment
- APP免费
15.4 Commissioning of Rotary-drum Slag Granulation Filter Equipment
- APP免费
15.5 Impact Baffle
- APP免费
16 Installation Engineering of Iron Treatment Equipment
- APP免费
16.1 General Provisions
- APP免费
16.2 Iron Casting Machine
- APP免费
16.3 Commissioning of Iron Casting Machine
- APP免费
16.4 Floor-type Tip-over Windlass
- APP免费
16.5 Commissioning of Floor-type Tip-over Windlass
- APP免费
16.6 Front Column
- APP免费
16.7 Plate-type Rotary Unloader
- APP免费
16.8 Commissioning of Plate-type Rotary Unloader
- APP免费
17 Installation Engineering of Milling Equipment
- APP免费
17.1 General Provisions
- APP免费
17.2 2-stage Vibrating Coke Crusher
- APP免费
17.3 Commissioning of 2-stage Vibrating Coke Crusher
- APP免费
17.4 Clay Mill
- APP免费
17.5 Commissioning of Clay Mill
- APP免费
17.6 Shaper
- APP免费
17.7 Commissioning of Shaper
- APP免费
18 Installation Engineering of Water Treatment Equipment
- APP免费
18.1 General Provisions
- APP免费
18.2 Top Trolley of Sedimentation Tank
- APP免费
18.3 Commissioning of Top Trolley of Sedimentation Tank
- APP免费
18.4 Float-type Oil Collector of Sedimentation Tank
- APP免费
18.5 Commissioning of Float-type Oil Collector of Sedimentation Tank
- APP免费
18.6 Horizontal Plate-and-frame Filter Press
- APP免费
18.7 Commissioning of Horizontal Plate-and-frame Filter Press
- APP免费
18.8 Pressure-type Cylinder-shaped Filter
- APP免费
18.9 Ion-exchange Resin Tower
- APP免费
18.10 Top Fan on Cooling Tower
- APP免费
18.11 Commissioning of Top Fan on Cooling Tower
- APP免费
18.12 Metal Tank
- APP免费
18.13 Vertical Mixer
- APP免费
18.14 Commissioning of Vertical Mixer
- APP免费
19 Overall Leakage Test for Blast Furnace System
- APP免费
19.1 General Provisions
- APP免费
19.2 Overall Leakage Test for Blast Furnace System
- APP免费
Appendix A Quality Record Sheet for Sub-divisional Works of Installation Acceptance of Metallurgical Machinery Ironmaking Equipment Engineering
- APP免费
Appendix B Quality Acceptance Record Sheet for Divisional Works of Installation for Metallurgical Machinery Ironmaking Equipment Engineering
- APP免费
Appendix C Quality Acceptance Record Sheet for Unit Works of Installation for Metallurgical Machinery Ironmaking Equipment Engineering
- APP免费
Appendix D No-load Commissioning Record of Metallurgical Machinery Ironmaking Equipment Engineering
- APP免费
Appendix E Pressure Test for Pressure-holding Equipment
- APP免费
Appendix F Sealing Requirements between valve petal and Valve Seat for Blow-off Valve,Equalizing Valve,Hot-blast stove Shut-off Valve,Gas Shut-off Valve and Ash Valve of Dust Collector
- APP免费
Explanation of Wording in This Code
- APP免费
Explanation for Provisions
- APP免费
1 General Provisions
- APP免费
2 Basic Provisions
- APP免费
3 Equipment Foundation,Anchor Bolts and Padding plate
- APP免费
3.1 General Provisions
- APP免费
3.2 Equipment Foundation
- APP免费
3.3 Anchor Bolt
- APP免费
3.4 Padding Plate
- APP免费
4 Mobilization of Equipments and Materials
- APP免费
4.1 General Provisions
- APP免费
4.2 Equipments and Elements
- APP免费
4.3 Raw Materials
- APP免费
5 Process Structural Steelwork
- APP免费
5.2 Welding
- APP免费
5.4 Fabrication of Frame,Corridors Truss
- APP免费
5.6 Fabrication of Shell
- APP免费
5.7 Installation of Frame
- APP免费
5.9 Installation of Shell
- APP免费
5.11 Painting Works for Process Steel Structure
- APP免费
6 Installation Engineering of Blast Furnace Body Equipment
- APP免费
6.2 Furnace Body Cooling Equipment
- APP免费
6.3 Tuyere Device
- APP免费
6.4 Slag Hole Device and Taphole Sleeve
- APP免费
7 Installation Engineering of Blast Furnace Bell-less Top Equipment
- APP免费
7.1 General Provisions
- APP免费
7.2 Transmission Gear Box With Distribution Chute
- APP免费
7.4 Valve Box
- APP免费
7.5 Charging Bucket
- APP免费
7.6 Receiving Hopper
- APP免费
7.10 Blow-off Valve,Equalizer Valve on Top
- APP免费
10 Installation Engineering of Tuyere Platform and Cast House Equipment
- APP免费
10.2 Hydraulic Clay Gun
- APP免费
10.4 Taphole Machine
- APP免费
10.6 Slag Stopper
- APP免费
10.11 Main Chute Cover Carriage
- APP免费
11 Installation Engineering of Hot-blast stove Equipment
- APP免费
11.5 Valve of Hot-blast Stove
- APP免费
12 Installation Engineering of Blast Furnace Air-blowing Equipment
- APP免费
12.2 Axial Blower
- APP免费
12.7 Valve
- APP免费
13 Installation Engineering of Gas Purification Equipment
- APP免费
13.6 Valve Group for Gas Pressure Regulating
- APP免费
13.8 Pressure-regulating Device of Circumferential Weld Scrubber
- APP免费
14 Installation Engineering of Blast Furnace Pulverized Coal Injection(PCI)Equipment
- APP免费
14.3 Raw-coal Bin and Pulverized Coal Tank
- APP免费
14.4 Pulverized Coal Collector
- APP免费
17 Installation Engineering of Milling Equipment
- APP免费
17.2 2-stage Vibrating Coke Crusher
- APP免费
17.6 Shaper
- APP免费
18 Installation Engineering of Water Treatment Equipment
- APP免费
18.1 General Provisions
- APP免费
18.12 Metal Tank
- APP免费
18.14 Commissioning of Vertical Mixer
- APP免费
19 Overall Leakage Test for Blast Furnace System
- APP免费
19.1 General Provisions
- APP免费
19.2 Overall Leakage Test for Blast Furnace System
更新时间:2020-09-24 18:15:53